Tuesday, July 2, 2019

Audit strategy vs audit plan

1. Document that the audit team will send accounts receivable confirmations Audit plan
2. Describe which controls will be tested Audit plan
3. Determine the basis of reporting for the financial statements Audit strategy
4. Determine materiality levels Audit strategy
5. Describe the methods to obtain an understanding of the entity and its environment sufficient to assess the risk of material misstatement Audit plan
6. Assign audit team personnel Audit strategy
7. Determine dates for fieldwork Audit strategy
8. Record which audit team members will perform which specific procedures Audit plan
9. Document the industry-specific reporting requirements Audit strategy
10. Budget audit team hours to high-risk areas Audit strategy

The audit strategy determines the characteristics of the engagement that defines its scope, allows the auditor to determine key dates and reporting objectives, and considers factors such as materiality and preliminary identification of areas where there may be a higher risk of material misstatement. The audit strategy helps the auditor assign resources.

The audit plan, however, is more detailed than the audit strategy and includes the nature, timing, and extent of audit procedures to be performed by audit team members in order to obtain sufficient appropriate audit evidence to reduce audit risk to an acceptably low level.


No comments:

Post a Comment