Clay Co. has considerable excess manufacturing capacity. A special job order’s cost sheet includes the following applied manufacturing overhead costs:

Clay Co. has considerable excess manufacturing capacity. A special job order’s cost sheet includes the following applied manufacturing overhead costs:

Fixed costs: $21,000
Variable costs: $33,000


The fixed costs include a normal $3,700 allocation for in-house design costs, although no in-house design will be done. Instead, the job will require the use of external designers costing $7,750. What is the total amount to be included in the calculation to determine the minimum acceptable price for the job?

$40,750

Given excess capacity, neither increased fixed costs nor opportunity costs are incurred by accepting the special order. Thus, the marginal cost of the order (the minimum acceptable price) is $40,750 ($33,000 variable costs + $7,750 cost of external design).

Sunday, July 11, 2021

Clifford’s pension fund will pay $40,000 per year for the next 5 years at the end of each year, after which the pension fund balance will be zero. The annual interest rate for the first 3 years is 3%, and the rate for the remaining 2 years is 4%. What is the current pension fund balance?

Clifford’s pension fund will pay $40,000 per year for the next 5 years at the end of each year, after which the pension fund balance will be zero. The annual interest rate for the first 3 years is 3%, and the rate for the remaining 2 years is 4%. What is the current pension fund balance?


Present value of 1 at 3% for 3 years:
0.915
Present value of 1 at 4% for 2 years:
0.925
Period(s)
Present value of an
ordinary annuity at 3%
Present value of an
ordinary annuity at 4%
1
0.97
0.96
2
1.91
1.89
3
2.83
2.78
4
3.72
3.63
5
4.58
4.45


$182,374

The five payments can be separated into two series of equal payments at equal intervals of time occurring at the end of each period (ordinary annuities). One is for 3 years at 3% and the other for 2 years at 4%. For the annuity for 2 years at 4%, the present value at the end of the third year is $75,600 ($40,000 × 1.89). The present value of this annuity currently is $69,174 ($75,600 × 0.915). For the annuity for 3 years at 3%, the present value currently is $113,200 ($40,000 × 2.83). The current pension fund balance therefore is $182,374 ($69,174 + $113,200).

A job-order cost system uses a predetermined factory overhead rate based on expected volume and expected fixed cost. At the end of the year, underapplied overhead might be explained by which of the following situations?

A job-order cost system uses a predetermined factory overhead rate based on expected volume and expected fixed cost. At the end of the year, underapplied overhead might be explained by which of the following situations?



Answer (B) is correct.
If too little fixed overhead is applied at the predetermined rate (expected fixed cost ÷ expected volume), the result is underapplied overhead (actual factory overhead exceeds overhead applied). If the actual and expected fixed costs are the same, but the actual volume is less than the expected (denominator) volume, overhead will be underapplied. If the actual volume equals expected volume but actual fixed costs exceed the expected (numerator) fixed costs, overhead is likewise underapplied.

Fact Pattern: Tidwell Corporation sells a single product for $20 per unit. All sales are on account, with 60% collected in the month of sale and 40% collected in the following month. A partial schedule of cash collections for January through March of the coming year reveals the following receipts for the period:

Fact Pattern:  Tidwell Corporation sells a single product for $20 per unit. All sales are on account, with 60% collected in the month of sale and 40% collected in the following month. A partial schedule of cash collections for January through March of the coming year reveals the following receipts for the period:

Cash Receipts
January
February
March
December receivables
$32,000
From January sales
54,000
$36,000
From February sales
66,000
$44,000

Other information includes the following:

  1. Inventories are maintained at 30% of the following month’s sales.
  2. Tidwell desires to keep a minimum cash balance of $15,000. Total payments in January are expected to be $106,500, which excludes $12,000 of depreciation expense. Any required borrowings are in multiples of $1,000.
  3. The December 31 balance sheet for the preceding year revealed a cash balance of $24,900.


March sales total $150,000. The number of units Tidwell must purchase in February is: 6,100 units


Projected sales for February total $110,000 ($66,000 + $44,000). Unit sales are thus expected to be 5,500 ($110,000 ÷ $20). March unit sales are projected at 7,500 ($150,000 ÷ $20). February purchases can thus be calculated as follows:
Needed for February sales
5,500
Add: 30% of March sales
2,250
Total units needed
7,750
Less: Beginning inventory
(1,650)
February purchases
6,100

IRR

 Select the project with IRR greater than capitalization rate (or discount rate).

Saturday, July 10, 2021

A company uses process costing to assign product costs. Available inventory information for a period is as follows:

A company uses process costing to assign product costs. Available inventory information for a period is as follows:

                            Inventory    Material   Conversion
                            (in Units)     Cost        Cost   
 Beginning                         0
 Started during the period    15,000     $75,000      $55,500
 Transferred out              13,500
 End of period                 1,500



The ending inventory was 25% complete as to the conversion cost. 100% of direct material was added at the beginning of the process. What was the total cost transferred out?

Equivalent unit for material cost = 13,500 + 1,500 = 15,000
Equivalent unit for conversion cost = 13,500 + (1,500 x 25%) = 13,875

Material cost per equivalent unit = 75,000 / 15,000 = $5
Conversion cost per equivalent unit = 55,500 / 13,875 = $4

Total cost transferred out = unit transferred out x (material cost per equivalent unit + conversion cost per equivalent unit) = 13,500 x $9 =  $121,500

Friday, July 9, 2021

M & P Tool has three service departments that support the production area. Outlined below is the estimated overhead by department for the upcoming year:

M & P Tool has three service departments that support the production area. Outlined below is the estimated overhead by department for the upcoming year:

                       Estimated   Number of
 Service Departments    Overhead   Employees
 Receiving              $25,000        2
 Repair                  35,000        2
 Tool                    10,000        1
 
 Production Departments
 Assembly                             25
 Bolting                              12



The Repair Department supports the greatest number of departments, followed by the Tool Department. Overhead cost is allocated to departments based upon the number of employees.

Using the step-down method of allocation, the allocation from the Repair Department to the Tool Department would be:

$875

The allocation would be $875, calculated as follows:

Allocation of Cost from Repair Department to Tool Department:
Employees in Tool Dept. = 1
Cost of Repair Dept. = $35,000
Total Non-repair Employees Excluding Rep. Dept. = 40


Allocation = Cost × (Tool employees/Sum of all non-repair employees)
= $35,000 × (1/(2 + 1 + 25 + 12))
= $35,000 × (1/40)
= $875