Kappa Construction began a construction project on January 1, year 4, with Alpha. Kappa recognized revenue over time. Use the documents provided in the Exhibits tab to complete the following schedules. Round all amounts to the nearest whole dollar or percentage (e.g., .78.6 = .79). Where necessary in subsequent calculations, use the rounded amount to perform calculations. If a number is a deduction, enter it preceded by a “-” sign.

Part 1:
Complete the schedule showing Kappa’s balances on the Alpha contract at December 31, year 4:
Accounts receivable, December 31, Year 4
$ 50,000
Costs and estimated earnings in excess of billings:
     Construction in progress
**$ 624,300
     Less: Billings
($ 395,000)
Costs and estimated earnings in excess of billings
$ 229,300

Part 2:
Prepare a schedule showing Kappa’s gross profit (loss) recognized for the years ended December 31, years 4 and 5, on the Alpha contract. (Enter "progress toward completion (%)" as a whole number (e.g., 45% = 45).)
For the Year Ended December 31,Year 4Year 5
Estimated gross profit (loss):

     Contract price
$ 750,000
$ 750,000
     Less: Total estimated costs 
($ 540,000)
($ 530,000)
     Total estimated gross profit
$ 210,000
$ 220,000
Progress toward completion:
     Total costs incurred to date
$ 450,000
$ 530,000
     Divide by total estimated costs
$ 540,000
$ 530,000
     Progress toward completion (%)
83
100
Gross profit (loss)
$ 174,300
$ 220,000
Less: Gross (profit) loss recognized in prior years
$ 0
($ 174,300)
Gross profit (loss) recognized
$ 174,300
$ 45,700

**Construction in progress (CIP) consists of contract costs incurred to date of $450,000 plus gross profit recognized to date of $174,300 (see below), unless there is a loss, which would be recognized in full in the period incurred. Both items can be found on Document #1: Alpha Job Cost Ledger.

$624,300 = $450,000 + $174,300